First and foremost... we listen
Bilfinger Berger Banner

Chemical Manufacturing Site Demolition

BIS Industrial Services was contacted to demolish three five-storey buildings on a Chemical Manufacturing site. The buildings were located adjacent to railway line, river and roadway.

Customer: Unspecified
Contract: Term Contract

Services Provided:
- Demolition
- Plant refurbishment
- Steam, Air, Gas, Water, Drains, Electricity

Value: £1.6m
Duration: 1 year and 2 months
Resources: 10,000 manhours without a single injury

Key Features: Contacted to demolish three five-storey buildings on a Chemical Manufacturing site. The buildings were located adjacent to railway line, river and roadway. All the buildings were heavily contaminated with asbestos and various hazardous chemicals.

Link-Up Po1nt LLoyds Register Quality Assurance ROSPA Presidents Award